Three-center build with active/active redundancy, a staggered 3-week training cycle (2 weeks classroom + 1 week nesting at 50% productive) and a live go-live checklist. Commencement 1 Oct 2026.
| Workstream | Prog. Dir. | Ops | WFM | Training | IT/Tel | Compl. |
|---|---|---|---|---|---|---|
| Facilities & Security | A | C | I | I | C | R |
| Technology & Telephony | A | C | I | I | R | C |
| Recruiting & Training | A | C | C | R | I | C |
| WFM & Reporting | A | C | R | I | C | I |
| Compliance & Go-Live | R/A | C | C | C | C | R |
| Steady-state operations | A | R | C | C | C | I |
| Class | Site | Classroom | Nesting | Production | Agents |
|---|---|---|---|---|---|
| Wave 1 · Cls 1–2 | El Salvador | Wk 1–2 | Wk 3 | Wk 4–5 | 60 |
| Wave 2 · Cls 3–4 | ES + Kingston | Wk 3–4 | Wk 5 | Wk 6–7 | 62 |
| Wave 3 · Cls 5–6 | ES + Kingston | Wk 5–6 | Wk 7 | Wk 8–9 | 62 |
| Wave 4 · Cls 7–8 | All centers | Wk 7–8 | Wk 9 | Wk 10–11 | 62 |
| Wave 5 · Cls 9–10 | All centers | Wk 9–10 | Wk 11 | Wk 12–13 | 64 |
| Wave 6 · Cls 11–12 | ES + Kingston | Wk 11–12 | Wk 13 | Wk 14–15 | 62 |
| Wave 7 · Cls 13–14 | All centers | Wk 13–14 | Wk 15 | Wk 16–17 | 64 |
| Wave 8 · Cls 15–17 | All centers | Wk 15–17 | Wk 18 | Wk 18–20 | 64 |
| Total to steady state · 17 classes across 3 centers | 500 | ||||